On-time arrival rate
On-time arrival rate is the percentage of visits that took place in a period where the technician arrived no later than the scheduled start plus a set grace period.
The inputs.
Arrival only, against the time promised to the customer.
- Arrived on timeArrival no later than the scheduled start plus your grace period, for example 15 minutes. Decide whether an early arrival counts; most companies count it as on time unless the customer could not give access.
- CohortVisits scheduled in the period that took place. Visits the customer cancelled or moved are left out; a visit your company moved after confirming it is measured against the original time.
- Worked exampleOf 388 visits that took place in March (12 customer cancellations left out), 341 arrived within 15 minutes of the scheduled start: 88%. One visit moved by the office from 9:00 to 13:00 after confirming and arriving at 13:05 counts as late against 9:00.
- Decision it informsWhether drive-time buffers and the first job of the day are planned realistically.
- Read withSchedule adherence, which also checks the finish time.
What to know.
How to calculate on-time arrival rate
On-time arrival rate equals visits that arrived on time divided by visits that took place in the period. On time means no later than the scheduled start plus a grace period you set once. Leave out visits the customer cancelled or moved; measure a visit your company moved after confirming it against the original time. Schedule adherence uses the same visits and also requires the visit to finish by its scheduled end.
Why on-time arrival rate matters for commercial contractors
Arrival is often the first thing a facilities team notices, and building access, escorts and tenant notices are arranged around it. When arrival windows are in the contract, they are measured as SLA compliance; when they are not, this rate is still how the customer experiences your reliability.
What tends to make arrivals late
Common causes are drive-time estimates that are too short, a first job that runs long and pushes the rest of the day, and stops booked out of geographic order. Check your late arrivals by time of day and by technician to see which applies.
How Thermal tracks on-time arrival rate
Each visit in Thermal records its scheduled start and the time the technician arrived. The operations dashboard's on-time arrival tile counts arrivals no later than 15 minutes after the scheduled start, and technician scorecards count arrivals within 15 minutes either side of it, so early arrivals are treated differently in the two views.
Questions about this term.
How is on-time arrival rate different from schedule adherence?
On-time arrival checks arrival only. Schedule adherence also requires the visit to finish by its scheduled end, so it is never higher than on-time arrival for the same visits.
Does an early arrival count as on time?
Decide and write it down. Most companies count it as on time unless the customer could not give access, in which case it is a scheduling problem of a different kind.
Does technician location tracking improve on-time arrival?
It can help dispatch react sooner, but it is not required to measure or improve the rate. Realistic drive times and sequencing do most of the work.
These numbers, on your own book.
If you want to see them calculated from real work orders and agreements rather than a spreadsheet, that's a demo.